§ 30.80.070. Off-Site Improvement Fees.  


Latest version.
  • Off-site improvement fees payable to the Director of Public Works shall be required as shown in Table 30.80-5.

    Table 30.80-5 Fee Schedule - Off-Site Improvement Fees
    Administrative Service Required Fee
    Soil/Asphalt Review
    Original Application Initial Submittal
    & 1 Review
    Every Review
    Over 2 Reviews
    Up to 5 Acres $750 $400
    Over 5 Acres & up to 40 Acres $2,000 $400
    Over 40 Acres & up to 320 Acres $4,000 $400
    Over 320 Acres $6,000 $400
    Improvement Plan Review
    Original Application $300, or 1.20 percent of the estimated construction cost , whichever is greater
    Revision of an Approved Plan $50/sheet
    Off-site Plan Rejection Additional 50% of plan check fee
    Impact Analysis Review—Traffic Study
    Original Application Initial Submittal
    & 1 Review
    Every Review
    Over 2 Reviews
    Up to 5 Acres $750 $400
    Over 5 Acres & up to 40 Acres $2,000 $400
    Over 40 Acres & up to 320 Acres $4,000 $400
    Over 320 Acres $6,000 $400
    Optional Traffic Mitigation $750, plus $150 per trip , prior to building permits or approval of improvement plans
    Impact Analysis Review - Drainage Study
    Original Application Initial Submittal
    & 1 Review
    Every Review
    Over 2 Reviews
    Up to 5 Acres $750 $400
    Over 5 Acres & up to 40 Acres $2,000 $400
    Over 40 Acres & up to 320 Acres $4,000 $400
    Over 320 Acres $6,000 $400
    Inspection Fees
    Offsite Permit
    First $30,000 $300 minimum, or 2.75 percent, whichever is greater
    Next $90,000 1.75 percent
    Over $120,000 1.00 percent
    Encroachment Permit Appropriate plancheck and inspection fees or $300.00 minimum whichever is greater
    Re-inspection Fee hourly rate for each re-inspection
    Re-test hourly rate
    Bond Replacement $500 prior to release of the existing bond
    Bond Reduction $500
    Improvement Agreement $50
    Traffic Control Plan $50
    Work Without A Permit 3x permit fee
    Structural Review $750 per 660 feet
    Right-of-Way Permit Violation $300
    Per Hour Rate $120
    Investigative Fees Hourly rate-minimum 3 hours
    Overtime Rate 1.5 hourly rate
    Flood Plain Determination $20 for each request for information as to whether or not a property is located within a Federal Emergency Management Agency defined special flood hazard area
    Clark County Supplement to Uniform Standard Drawings and Specifications $10
    Additional Requirements:
    1. As determined on the construction bond estimate form, and as approved by the Director of Public Works.
    2. Resubmittal shall be required if plans do not contain sufficient information for a complete review, have been substantially redesigned, or if required corrections are not submitted within one (1) year of notification.
    3. As defined in Chapter 30.52.055(b).
    4. Based on the estimated construction costs as determined by the Director of Public Works.
    5. Additional fees may be required to provide for overtime or night work and must be paid prior to final acceptance of the work.
    Refund Policy: Per 30.80.020(b)

     

    (Ord. 3518 § 16 (part), 2007; Ord. 3296 § 10 (part), 2005; Ord. 2849 § 1, 2003; Ord. 2769 §§ 110—111, 2002; Ord. 2482 § 19 (part), 2000; Ord. 2481 § 3 (part), 2000)